Solve the following sequencing problem. Determine minimum elapsed time. Also determine idle time for machines A, B and C. (Time in min.) -
JOBS | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
---|---|---|---|---|---|---|---|
A | 3 | 8 | 7 | 4 | 9 | 8 | 3 |
B | 4 | 3 | 2 | 5 | 1 | 4 | 2 |
C | 6 | 7 | 5 | 11 | 5 | 6 | 7 |