written 8.4 years ago by | • modified 4.0 years ago |
We have six jobs, each of which must go through machine A, B & C in the order of ABC. Processing times (in hours) are given: - | Job | 1 | 2 | 3 | 4 | 5 | 6 | |-----------|---|---|---|---|----|---| | Machine A | 8 | 3 | 7 | 2 | 5 | 1 | | Machine B | 3 | 4 | 5 | 2 | 1 | 6 | | Machine C | 8 | 7 | 6 | 9 | 10 | 9 |
Determine minimum elapsed time, idle time for machines, and idle time for jobs. -