0
2.8kviews
Difference between Critical path method and Gantt chart
1 Answer
| written 3.6 years ago by |
Critical path method (CPM):
It visualizes critical and non-critical paths and calculates project duration.
It is dsplayed as network diagram with linked boxes.
CPM doesn’t show resources required
CPM plots activities on network diagram without timescale.
Gantt chart:
It visualizes how project activities are progressing.
Gantt chart is displayed as horizontal bar chart.
It shows resources required for each activity.
It plots activities on a timescale.