Quantity of earthwork

Workout the quantity of earthwork for a portion of a road.

  1. Top width of formation = 12m
  2. R.L of formation at zero chainage = 51.4m
  3. Falling gradient = 1 in 200
  4. Side slope 1V:2H (Banking)

    1v:1.5H (Cutting)

Chainage 0 30 60 90 120 150 180
R.L of Gr (m) 50.8 50.6 50.7 51.2 51.4 51.3 51

Mumbai University > CIVIL > Sem 7 > Quantity survey Estimation and valuation

Marks: 12 M

Year: Dec 2014

1 Answer
0
53views

Enbarkment

Abanking=bh+sh2=6h+2h2

enter image description here

Cutting

Acut=bh+sh2=5.5h+1.5h2

enter image description here

Falling gradient – 1: 200

1200=x30x=0.15

enter image description here

x30x=0.40.25x=18.46

enter image description here