Item No Description of work Qty Unit Rate,Rs. Unit of rate Amount
1. P.C.C(1:2:4) in foundation 9.7 Cu.m 84 Per cu.m 814.8
2. Ist class brickwork in foundation in C. M (1:4) 47.6 cu.m 2310 Per cu.m 109956
3. 2.5 thick D.p.C.(1:3:6) 15.6 cu.m 98 Per cu m 1528.8
4. 12 mm thick internal plaster in C.M(1:5) 173.8 Sq.m 15 Per sq.m 2607.3
- - - - - Total = Rs. 114906.9

Add 5% contingency = Rs 5745.34

Add 2.5% work charge= Rs. 2872.67

Total Estimate cost = Rs. 123524.91 ≈123525