Prepare an abstract for all items

Mumbai University > CIVIL > Sem 7 > Quantity survey Estimation and valuation

Marks: 6 M

Year: May 2013

1 Answer
0
2views
Srno. Description of work Qty Unit Rate,Rs. Unit of rate Amount
1. UCR in,Masonry in,CM (1:5) 58.46 Cu.m 350 Per cu.m 20461
2. $1{st}$ class brickwork in super structure in CM (1:4) 39.61 cu.m 3850 Per cu.m 152498.5
3. D.P.C(2.5 cm thk) in 1:2:4 15.09 sq.m 94 Per sq.m 1418.46
4. 12mm thk Internal plaster in CM 1:4 190.65 Sq.m 13.5 Per sq.m 2573.7
- - - - - Total = Rs. 176951.73

Total estimated $= Add \ \ 5 \% \ contingency + work \ \ charge 2.5 \% \\ \; = Rs. 8847.58+ Rs. 4423.79 \\ \; = Rs. 190223.1$

Cost = Rs. 190224