Prepare abstract for all items

Mumbai University > CIVIL > Sem 7 > Quantity survey Estimation and valuation

Marks: 8 M

Year: Dec 2012

1 Answer
0
2views
Sr no. Description of work Qty Unit Rate,Rs. Unit of rate Amount
1. UCR,(1:5) Masonry in sub structure 62.25 Cu.m 350 Per cu.m 21787.5
2. D.C.C(2.5 cm thk) in 1:2:4 22.14 Sq.m 94 Per sq.m 2081.16
3. $1{st}$ class brickwork in super structure in CM (1:4) 58.6 Cu.m 3850 Per cu.m 225610
4. Internal plaster in CM 1:4 243.2 Sq.m 13.5 Per sq.m 3283.2
- - - - - Total = Rs. 252761.86

Total estimated = $Add \ \ 5 \% \ \ contingency + work \ \ charge \ \ 2.5 \% \\ \; = Rs. 12638.09 + Rs. 6319.04 \\ \; = Rs. 271718.99$

Cost = Rs. 271719