Prepare abstract of cost for the items of work

Mumbai University > CIVIL > Sem 7 > Quantity survey Estimation and valuation

Marks: 8 M

Year: May 2012

1 Answer
0
44views

Note:

  1. Abstract is a balance sheet of the final amount that will incure for the given items of work.
  2. Rate of a particular item is totally assumed.
  3. Take 5% contingency.
  4. Take 2.5% work charge establishment.
Sr no. Description of work Qty Unit Rate,Rs. Unit of rate Amount
1. Earthwork in excavation for foundation 60.86 Cu.m 6.5 Per cu.m 395.59
2. P.C.C (1:2:4),For foundation bed 8.69 Cu.m 84 Per cu.m 729.96
3. $1^{st}$ class brickwork in super structure 38.53 Cu.m 3850 Per cu.m 148341
4. D.P.C (25cm thk) in 1:3:6 15.39 Cu.m 98 Per cu.m 1509
- - - - - Total = Rs. 150976

Total estimated $= Add \ \ 5 \% \ \ contingency \ \ + \ \ work \ \ charge 2.5 \% \\ \; \\ = Rs. 7548.8 + Rs. 3774.4 \\ \;\\ = Rs. 162299.2$

Cost = Rs. 162300