CBRI method
This information is useful for preparation of building cost index, preplanning of materials and labour requirement in a building project. Equations for Materials & Labour requirement for structure in Four-storeyed (RCC Frames Building),
A=Plinth area in sq.
Materials | Equations | Labours (in days) | Equations |
---|---|---|---|
Cement(tones) | 0.0204A- 0.014 | Mason | 0.023A |
Sand (cu.m.) | 0.036A | Carpenter | 0.05A |
Coarse aggregate (cu.m.) | 0.071A-0.01 | Blacksmith | -1.6+0.1A-0.0003A2 |
Steel (kg) | -171+10.46A-0.041A2 | Mazdoor | 0.343A |