0
13kviews
Explain CBRI method.
1 Answer
0
860views

CBRI method

  1. To form the basis for calculation of materials and labour, CBRI has recommended the following formulae which after a study of the specifications have been selected for this analysis.
  2. The table as given below is for buildings of different shapes and plinth areas varying from 30 to 300 sq. these are the average constant.
  3. This information is useful for preparation of building cost index, preplanning of materials and labour requirement in a building project. Equations for Materials & Labour requirement for structure in Four-storeyed (RCC Frames Building),

    A=Plinth area in sq.

Materials Equations Labours (in days) Equations
Cement(tones) 0.0204A- 0.014 Mason 0.023A
Sand (cu.m.) 0.036A Carpenter 0.05A
Coarse aggregate (cu.m.) 0.071A-0.01 Blacksmith -1.6+0.1A-0.0003A2
Steel (kg) -171+10.46A-0.041A2 Mazdoor 0.343A