0
2.2kviews
Suggest the degree of workability in terms of slump for the following: i) Pavements using pavers ii) Canal lining iii) Heavily reinforced sections iv) In-situ piling
1 Answer
0
183views

Degree of workability in terms of slump for the following:

i) Pavements using pavers: 25-75 mm

ii) Canal lining: 70-80 mm

iii) Heavily reinforced sections: 50-100 mm

iv) In-situ piling: 100-150 mm

Please log in to add an answer.