1) Earthwork in an excavation in the foundation. 2) Lime concrete in foundation 3) First class brickwork in cement mortar (1:4) in foundation and plinth. 4) First class brickwork in cement mortar (1:6) in superstructure. Neglect step.
(A) By centre line method:
(a) Length of centre line for mainwalls = 2{5.0+2802)+(4+2808) = 19.20m (b) Length of centre line for verandah walls, sides = 2(1.5+.803+.208)=3.50m
Number of joints = 2nos
Front = 3+2*.208=3.20m
Total = 6.70m
Note that a join occurs at a place where three walls join.
Description | No | L m | B m | H m | Quantity | Total | Explanatory notes |
---|---|---|---|---|---|---|---|
1. Earthwork in excavation | 1 1 | 19.20 5.80 | .90 .46 | 1.00 .70 | 17.28 1.87 | 19.15 cu m | Length of verandah is reduced by half trench width 5.80=6.70-2*. |
2.Lime concrete in foundation | 1 1 | 19.20 6.10 | .90 .46 | .30 .20 | 5.18 .56 | 5.74 cu m | Lime concrete joins with 60cm brick layer of main wall 6.10 = 6.70-2*.803 |
3. First class brickwork in foundation and plinth (1:4) a) Main walls 60cm layer 50cm layer 40cm layer b)Verandah wall, portion joins with 60cm layer of main wall 50cm layer of main wall 40cm layer of main wall | 1 1 1 1 1 1 | 19.20 19.20 19.206.10 6.20 6.30 | .60 .50 .40 .30 .30 .30 | .30 .20 .80 .10 .20 .80 | 3.46 1.92 6.14 11.52 .18 .37 1.51 | 13.58cu m | 6.10=6.70-2.602 6.20=6.70-2.802 6.30=6.70-2*.402 |
First class brickwork in supersructure walls a) main walls b)verandah walls | 1 1 | 19.20 6.40 | .30 .20 | 3.60 2.80 | 20.74 3.58 | 24.32 | 6.40=6.70-2* |
Deducation for door opening, D Window openings,W Verandah openings, sides Verandah openings, front Lintel at main wal Lintel at verandah | 1 5 2 1 1 1 | 1.10 1.00 1.50 3.00 19.20 6.70 | .30 .30 .20 .20 .30 .20 | 2.10 1.50 2.40 2.40 .15 .15 | .69 (-ve) 2.25 1.44 1.44 .86 .18 | " " " " " 17.46 cu m | Verandah lintel with 15cm bearing at the ends in main wall 6.70=6.4+2*.15 6.4 as that for 20cm wall in 4(b) |