written 5.3 years ago by |
In western suburb of Mumbai[RCC framed structure]
Plot area = 60*30m
FSI = 1.5
Building is G+3
Consider foundation cost as 20% of the cost of superstructure.
Allow 20% of building cost for all services.
Allow 2.5% of overall cost for consultant fees.
Consider 5% provision for contingencies.
Given:
Plot area=60*30
FSI = 1.5
FSI = $\frac{builtup \hspace{1mm} area }{total\hspace{1mm}plot\hspace{1mm}area\hspace{1mm}}$
Total built up area = FSI * total plot area = 1.5*2800 = 2700 sq.m
Assuming rate of construction in western suburb of Mumbai as Rs.22000 per sq.m
Cost of building = builtup area * builtup area rate = 2700*22000=5cr 94 lac
Total cost of building = cost of superstructure + cost of foundation = 5cr 94 lac + 20% of 5cr 94 lac
=71280000 = 7 cr 122lac 80 thousand.
Add 20% of total building cost for all services.
Overall cost of buildinng = total cost of building + 20% of total cost = 7cr 12lac 80 thousand + 20% of 71280000
= 85536000
Final grand approximate cost = overall cost + consultant fees + contingencies
= 85536000 + 205% of OC + 5% of OC
= 9cr 18lac 48 thousand.