Draw AON diagram and find the activities on critical path. Calculate minimum Overall project completion time. What is float time associated with each of non-critical activities?
written 8.5 years ago by | • modified 4.0 years ago |
Activity | Duration(wrks) | Immediate Predecessor |
---|---|---|
A | 2 | - |
B | 3 | - |
C | 4 | A |
D | 3 | A,B |
E | 8 | C,D |
F | 3 | C |
G | 2 | E |
H | 3 | F,G |
ADD COMMENT
EDIT
1 Answer