There are three important stages of planning of a construction project are:
1] Pre-construction stage –
Analyse clients project related requirement.
Prepare the design briefly in terms of function ability, cost time, quality and safety.
Develop project organization chart.
Develop project control system.
Establishment of project communication and reporting system.
Preparation of work breakdown structure.
Preparation of design/drawing deliverable schedule.
Coordination and follow-up with the design.
Consultant for their inputs.
Lead project meetings as necessary for review of progress.
Preparation of procurement plan.
Conducting pre-bid meetings and feedback for completeness of tender specifications and technical parameters.
2] Construction stage –
Full time supervision of all construction works/ activities for the project.
On site design coordination and issue of drawings clarification.
Organize approval to contractor prodiucement data, samples or material etc.
Monitoring progress of work with the master construction schedule of project which is prepared in pre-construction stage.
3] post construction stage –
Advice about probable data of substantial completion.
Preparing and addressing the schedule of detects.
Provide assistance in testing and commissioning of the facility.
Re conciliation and certification of final bills of contractors, suppliers, vendors and consultants.
Preparation of project close out report including all the bills, drawing, specification etc.
Addressing any queries during defects liability periods.
Co-ordination with the contractor to rectify the defects during liability periods