Activity data for a small project is given in the following table
written 5.7 years ago by | • modified 4.6 years ago |
Activity | A | B | C | D | E | F | G | H | I |
---|---|---|---|---|---|---|---|---|---|
Preceding Activity | -- | -- | -- | A | B | C | D, E | B | H, F |
Duration (days) | 3 | 5 | 4 | 2 | 3 | 9 | 8 | 7 | 9 |
i- Draw AOA Network
ii- Work out activity times and floats
iii- Determine project duration and critical