Activity data for a small project is given in the following table
Activity A B C D E F G H I
Preceding Activity -- -- -- A B C D, E B H, F
Duration (days) 3 5 4 2 3 9 8 7 9

i- Draw AOA Network

ii- Work out activity times and floats

iii- Determine project duration and critical