The following table shows the details of activities of a small work. Construct the network of the project.Determine optimum project cost & optimum duration. Indirect cost/day = Rs.700 /-
Activity Predecessor Normal Normal Crash Crash
Time (days) Cost (Rs) Time (days) Cost (Rs)
A ---- 9 8000 6 9500
B ---- 5 5000 3 5500
C B 5 5000 3 5500
D A 7 4000 4 7500
E A 5 5500 3 7000
F D 6 8000 4 10000