Mile stone Chart
1 Answer
0
20views
  • A milestone is used to represent groups of activities or significant events or commitments in the project.

  • A milestone chart shows a group of milestones in an organized way similar to a Gantt chart with one milestone per line vertically with a description on the left and the milestone located horizontally along a time scale showing when it occurs.

  • Milestones differ from the bars in a Gantt chart in that they show only a single date and are usually depicted as a triangle instead of a bar.

  • Milestones can be shown in various colours depicting the status of the milestone.

  • Milestones can also appear on Gautt chats, project management software supports the placement of milestone on Ghant charts and other project reports and displays generated by the software.