Table below shows activities, their durations and labour requirements:
written 5.7 years ago by | • modified 4.6 years ago |
Activity | Duration | Labours |
---|---|---|
A (10-20) | 4 | 3 |
B (10-30) | 5 | 4 |
C (20-50) | 7 | 2 |
D (30-40) | 5 | 5 |
E (30-50) | 4 | 3 |
F (40-50) | 6 | 3 |
Draw Time scaled version network. Workout daily requirement of labours for all activities. Prepare histograms of EST & LST schedule. Which schedule you will prefer & why?