0
1.0kviews
The following table shows the details of activities of a small project. Calculate the optimum project cost & project duration. Indirect cost = Rs. 1500 / per day
Activity Predecessor Normal Normal Crash Crash
Time (days) Cost (Rs) Time (days) Cost (Rs)
A ---- 9 8000 6 9500
B ---- 5 5000 3 5500
C B 7 6500 4 10500
D A 6 7000 4 10000
E A 5 4500 3 7500
F D 9 5500 5 9000
Please log in to add an answer.