Following table shows the activities, their interdependence and the durations
written 5.7 years ago by | modified 2.7 years ago by |
Activity | A | B | C | D | E | F | G | H |
---|---|---|---|---|---|---|---|---|
Preceding Activity | -- | A | A | B | B | C, E | D, F | C, E |
Duration (days) | 5 | 7 | 9 | 4 | 6 | 7 | 5 | 4 |
a) Draw a A-O-A network
b) Work out all activity times and floats
c) Identify the critical path and the project duration