Following is the data associated with a small Project

Activity 1-2 1-3 1-4 2-5 3-5 4-6 5-6
To(weekss) 1 1 2 1 2 2 3
Tm(weeks) 1 4 2 1 5 5 6
Tp(weeks) 7 7 8 1 14 8 15

Z -3 -2 -1 0 1 2 3
P(%) 0.13 2.28 15.87 50 84.13 97.72 99.87

Determine standard Deviation & Variance of the Project. Also determine the Probability of completing the project at :-
i) Expected duration ii) 3 weeks earlier than expected duraiton
iii) 3 weeks later than expected duration.

1 Answer
0
4views

enter image description here

1) Expected duration is 17 days.

2) 3 weeks earlier than E D

enter image description here

Variance = $\sqrt{6^2} = 2$

Z = $\frac{S.T – E D}{Variance}$

Z = $\frac{14-17}{3}$

= - 1

Z = 15.87

So the probability of completing the project three weeks earlier than E D is 15.87 %

3) 3 weeks later than E. D

Z = $\frac{S.T – E.D}{6}$

Z = $\frac{20-17}{3}$

= 1

Z = 84.13

So the probability of completing the project 3 weeks earlier than E D is 84.13