Following is the data associated with small construction Project.
written 5.6 years ago by | • modified 4.6 years ago |
Draw Network. Calculate event Times. Identify Critical Path, Also determine Values of all types of floats.
Activity | A | B | C | D | E | F | G |
Preceeding Activity | ----- | A | A | A | B | D | C,E,F |
Duration(days). | 5 | 4 | 7 | 5 | 3 | 4 | 7 |
ADD COMMENT
EDIT
1 Answer