Following is the data associated with small construction Project.

Draw Network. Calculate event Times. Identify Critical Path, Also determine Values of all types of floats.

Activity A B C D E F G
Preceeding  Activity ----- A A A B D C,E,F
Duration(days). 5 4 7 5 3 4 7