Man power planning
A manpower can be defined as the number of people that is required to complete the tsk and is assigned to an activity. It is suggested to create and ace locate the minimum number of resource to activities. When the project schedule is completed with the activity, duration, start and finish date s for each activity and for the whole project, next step is to define and assign resource to the activities then to find the estimated cost for the activities and for the whole project is the work is done using analysis of rate CPWD.
Name of the Activity | Unit | Mason | Belder | Bhisti |
---|---|---|---|---|
PCC | 1 cum | 0.10 day | 1.63day | 0.70day |
R C C (footing) | 1 cum | 0.17 day | 2.00 day | 0.90 day |
R C C (plinth Beam) | 1 cum | 0.17 day | 2.00 day | 0.90 day |
R C C ( column) | 1 cum | 0.17 day | 2.00 day | 0.90 |