Following is the data of the associated with PERT Project.
Activity A B C D E F G
Preceding activity -- -- A B A B C & D
to (days) 6 5 4 4 4 2 4
tm (days) 9 8 7 7 7 5 10
tp (days) 12 17 22 16 10 8 22
Z -3 -2 -1 0 1 2 3
P (%) 0.13 2.28 15.87 50 84.13 97.72 99.87

i) Determine the variance of the project.

ii) What is the probability of completing the project in 29 days?

iii) What is the scheduled duration with 90% probability?

1 Answer
0
112views

enter image description here

enter image description here

Critical path = A – C – G

= 1 – 2 – 4 – 5

1] variance = 6 = 7 (for critical path)

2] probability of completing the project in 29 days

Z=S.TPDE

Z=292962=04.36

Z=0

50% …