Details of activities of a construction project are given below.

Identify critical path. Determine values of total float, free float & independent float of all the activities.

Activity A B C D E F G H I J K L M N
Preceding Activity -- A A B D D D B C, E G F, I, J K G, H M
Duration (days) 5 2 6 12 10 9 5 9 1 2 3 9 7 9
1 Answer
0
43views

enter image description here

Critical path = 1 – 2 – 4 – 6

= 1 - 2 - 3 - 5 - 4 - 6

= 1 – 2 – 3 – 6

= 1 – 2 – 3 – 5 – 6

= A – B – D – F – I

= A – C – I

= A – B – D – F

enter image description here