written 5.6 years ago by
teamques10
★ 68k
|
•
modified 5.6 years ago
|
Solution:
Activity |
Immediate predecessor |
Normal duration(weeks) |
Normal Cost(Rs) |
Crash duration (weeks) |
Crash cost(Rs) |
Cost slope $ ( \frac{C_c - N_c}{N_T - C_T} )$ |
A |
- |
3 |
3000 |
1 |
4500 |
750 |
B |
A |
2 |
5000 |
1 |
8000 |
3000 |
C |
B |
4 |
2000 |
2 |
4000 |
1000 |
D |
B |
3 |
7000 |
1 |
10,000 |
1500 |
E |
B |
2 |
12,500 |
2 |
12,500 |
0 |
F |
C |
3 |
10,000 |
1 |
13,500 |
1500 |
G |
D,E |
5 |
6500 |
3 |
9000 |
1250 |
H |
F |
4 |
4300 ------ 50,300 |
2 |
8000 |
1850 |
1st Iteration:
Starting activity - A
Ending: H, G
A |
B |
Project duration: 16 weeks |
Normal cost = 50,300 |
Critical path: 1 - 2 - 3 - 4 - 7 8 = 3 + 2 + 4 + 3 + 4 = 16 weeks |
Indirect cost = 3000 X 16 T.C = 98,300 |
Critical path |
Critical activity |
Crash limit |
Cost slope |
1 - 2 - 3 - 4 - 7 - 8 |
1 - 2(A) |
2 |
750* |
|
2 - 3 (B) |
1 |
3000 |
|
3 - 4 (C) |
2 |
1000 |
|
4 - 7 (F) |
2 |
1500 |
|
7 - 8 (H) |
2 |
1850 |
Crash activity A by one week
2nd Iteration:
A - B - C - F - H = 2 +2 + 4 + 3 + 4 = 15 week
cost = previous cost + cost slope - Indirect cost
= 98300 + 750 X 1 - 3000 X 1
= Rs.96,050
Critical path |
Critical activity |
Crash limit |
Cost slope |
1 - 2 - 3 - 4 - 7 - 8 |
A |
1 |
750* |
|
B |
1 |
3000 |
|
C |
2 |
1000 |
|
F |
2 |
1500 |
|
H |
2 |
1850 |
3rd Iteration:
A - B - C - F - H = 1 + 2 + 4 + 3 + 4 = 14 week
cost = previous cost + cost slope + Indirect cost
= 96050 + 750 X 1 - 3000 X 1
= Rs.93,800
Critical path |
Critical activity |
Crash limit |
Cost slope |
1 - 2 - 3 - 4 - 7 - 8 |
A |
0 |
750 |
|
B |
1 |
3000 |
|
C |
2 |
1000* |
|
F |
2 |
1500 |
|
H |
2 |
1850 |
Crash activity 'C' by two week
4th Iteration:
A - B - C - F - H = 1 + 2 + 2 + 3 + 4 = 12 week
cost = previous cost + cost slope - Indirect cost
= 93800 + 1000 X 2 - 3000 X 2
= Rs. 89,800
Critical path |
Critical activity |
Crash limit |
Cost slope |
1 - 2 - 3 - 4 - 7 - 8 |
A |
0 |
750* |
|
B |
1 |
3000 |
|
C |
0 |
1000 |
|
F |
2 |
1500* |
|
H |
2 |
1850 |
Crash activity F by one week
5th Iteration:
A - B - D - d1 -c1 = 1 + 2 + 3 + 0 + 5 = 11 week
A - B - C - F - H = 1 + 2 + 2 + 2 + 4 = 11 week
cost = 89800 + 1500 X 1 - 3000 X 1 = Rs. 88300
Critical path |
Critical activity |
Crash limit |
Cost slope |
1 - 2 - 3 - 4 - 7 - 8 |
A |
0 |
750 |
|
B |
1 |
3000 |
|
C |
0 |
1000 |
|
F |
1 |
1500 |
|
H |
2 |
1850 |
1 - 2 - 3 - 5 - 6 - 8 |
A |
0 |
750 |
|
B |
1 |
3000 |
|
D |
2 |
1500 |
|
G |
2 |
1250 |
Crash activity F and G simultaneously
6th Iteration:
Cost: Rs. 88,050