For a small project, prepare a resource histogram based on EST and LST schedule. Comment on the suitability of distribution on above methods.
Activity A B C D E F G
Preceding activity - - - A B C E
Duration (days) 4 5 3 4 5 3 7
Masons required 3 4 4 3 2 4 8

Smoothen the resources depending upon the peak demands.

1 Answer
0
18views

Starting activity: A,B,C

Ending activity: D, E, F

enter image description here

Critical path: 1 - 3 - 5 - 6

Critical activity: B - E - G

As per LFT, it is found that peak demand of carpentor goes on decreasing which results in smoothening of the carpentors requirements.

As per LFT …