Following table shows the activities, their interdependence and the duration
written 5.7 years ago by | • modified 4.6 years ago |
Activity | A | B | C | D | E | F | G | H | K | L | M |
---|---|---|---|---|---|---|---|---|---|---|---|
Preceding activity | - | - | - | A | B | B | C | C | F | G | H,K,L |
Duration (days) | 3 | 3 | 3 | 18 | 4 | 15 | 8 | 11 | 7 | 5 | 7 |
a) Draw a A-O-A network
b) Work out all activity times and floats
c) Identify the critical path and the project duration.