The workmen in an engineering firm are expected to work for 400 minutes in a shift of 8 hours. The remaining time is meant for rest and personal needs, etc.

i) Estimate the standard time per piece of a job whose normal time is 2 minutes.

ii) Find number of pieces to be produced per day.

iii) If the workmen engaged on the above job produced 180 pieces in the shift, what 1s their efficiency?

1 Answer
0
307views

Total minutes in a shift $=8 \times 60=480$

Normal Time $=2$ minutes

Allowances $=480-400=80$ minutes

Percentage Allowance $=\frac{\text {Rest timing } \times 100}{\text { Available work timing}}$ $=\frac{80 \times 100}{400}=20 \%$

$\begin{aligned} \text {a. Standard time } &=\text { Normal time }(1+\text { allowance percentage })\\ &=2(1+0.20)=2.4 \text { minutes } \end{aligned}$

$\begin{aligned} \text {b. No. of pieces to be produced per day} &=\frac{\text { Total time available for production }}{\text {standard time per piece}} \\ &=\frac{480}{2.4}=200 \ \text{pieces/day} \end{aligned}$

$\begin{aligned} \text {c. Operator's efficiency} &=\frac{\text { Produced Quantity } X 100}{\text { Standard production quantity}} \\ &= \frac{180 \times 100}{200}=90 \% \end{aligned}$