If a worker takes 15 minutes as a standard time for a job in which total allowance is 20% of normal time. If the rating of worker is 100%.
written 5.7 years ago by | • modified 5.7 years ago |
Find the actual time required by the worker.
Subject: Production Engineering and Robotics
Difficulty: Medium
Marks: 6 Marks
ADD COMMENT