Draw AON diagram and find the activities on critical path. Calculate minimum Overall project completion time. What is float time associated with each of non-critical activities?
Activity Duration(wrks) Immediate Predecessor
A 2 ---
B 3 ---
C 4 A
D 3 A,B
E 8 C,D
F 3 C
G 2 E
H 3 F,G

Mumbai University > Information Technology > Sem 7 > Software Project Management

Marks: 10 M

Year: May 2013

1 Answer
0
7views

The overall minimum project completion time is 19 weeks. There are two critical paths and the activities on them are – A, B, C, D, E, G, H. The float time associated with the only non-critical activity F is 7.