2.0kviews
The following data refers to the study conducted for an operation. Table shows actual time for the elements in minutes.
written 5.9 years ago by | modified 3.0 years ago by |
i) Element no. 2 is machine element.
ii) Consider observation as abnormal & delete the same if they are more than 20% of average time of the element.
iii) Take performance rating as 110.
iv) Assume personal & fatigue allowance as 29% of the normal time.
Estimate the basic time & standard time for the operation.
Elements | Cycle (minutes) | |||
---|---|---|---|---|
1 | 3.5 | 3.4 | 3.3 | 3.5 |
2 | 4.5 | 4.6 | 4.5 | 4.5 |
3 | 2.4 | 2.2 | 2.3 | 2.3 |
4 | 1.5 | 1.6 | 3.5 | 1.6 |