The following data refers to the study conducted for an operation. Table shows actual time for the elements in minutes.

i) Element no. 2 is machine element. 

ii) Consider observation as abnormal & delete the same if they are more than 20% of average time of the element.

iii) Take performance rating as 110. 

iv) Assume personal & fatigue allowance as 29% of the normal time. 

Estimate the basic time & standard time for the operation.

Elements Cycle (minutes)
1 3.5 3.4 3.3 3.5
2 4.5 4.6 4.5 4.5
3 2.4 2.2 2.3 2.3
4 1.5 1.6 3.5 1.6