15mm Thick plastering

Consider 100m²

Wet volume of concrete =151000×100=1.5m³

Add 30% for joint filling, Undulations, Wastage

=(30100×1.5)+1.5=1.95m³

Add 20% for dry volume

=(20100×1.95)+1.95=1.95m³

Cement Quantity =2.34(1+4)=0.468m³

No. of bags = 13.48bags

Quantity of sand = 4×0.468 = 1.872 m³

enter image description here

Rate per m³=24922.48100=Rs.249.22/m²