Perform rate analysis for internal plastering 15mm thick in CM 1:4 including scaffolding
1 Answer
written 6.2 years ago by |
15mm Thick plastering
Consider 100m²
Wet volume of concrete $=\frac{15}{1000}×100=1.5m³$
Add 30% for joint filling, Undulations, Wastage
$=\bigg(\frac{30}{100}×1.5\bigg)+1.5=1.95m³$
Add 20% for dry volume
$=\bigg(\frac{20}{100}×1.95\bigg)+1.95=1.95m³$
Cement Quantity $=\frac{2.34}{(1+4)}=0.468m³$
No. of bags = 13.48bags
Quantity of sand = 4×0.468 = 1.872 m³
Rate per $m³=\frac{24922.48}{100}=Rs.249.22/m²$