0
19kviews
Perform rate analysis for internal plastering 15mm thick in CM 1:4 including scaffolding
1 Answer
written 6.5 years ago by |
15mm Thick plastering
Consider 100m²
Wet volume of concrete =151000×100=1.5m³
Add 30% for joint filling, Undulations, Wastage
=(30100×1.5)+1.5=1.95m³
Add 20% for dry volume
=(20100×1.95)+1.95=1.95m³
Cement Quantity =2.34(1+4)=0.468m³
No. of bags = 13.48bags
Quantity of sand = 4×0.468 = 1.872 m³
Rate per m³=24922.48100=Rs.249.22/m²