a) Draw precedence diagram b) Perform forward and backward path calculation c) Find critical path

Subject:- Software Project Managment

Title:- Project Time Managment

Difficulty:- Hard

Activity Predecessor Duration
A 3
B A(FS2) 2
C A(SS) 2
D B(SS1) 4
E C(SF3) 1
F C(FF3) 2
G D(SS1),E 4
H F(SF2),G 3
1 Answer
0
40views

The overall minimum project completion time is 14 Days. There is one critical paths and the activities on them are – A, B, D, G, H.

The float time associated are C is 4, E is 4, F is 9

In the figure given below,

Es=Early start

Ls=Late start

Ef=Early finish

Lf=Late finish

Ft=Float time