Explain briefly about the selection site for Installation for Biogas plant.

Subject:- Renewable Energy Sources

Topic:- Wind Energy

Difficulty:- High

1 Answer
0
102views

1) Should have minimum distance between the points of gas production & gas Consumption.

2) Should be contracted in open space to utilize sun energy since the biogas production is high above $25^o C$ temperature.

3) It should be constructed at least 10m away from wells to avoid seepage of fermented slurry.

4) Sufficient quantity of water along with biomass is available at site for formation of biomass slurry.

5) Sufficient space is available for its operation maintenance.