Activity |
Normal Duration (days) |
Normal Cost (Rs.) |
Crash Duration (days) |
Crash Cost (Rs.) |
Cost Slope |
1-2 |
7 |
7500 |
4 |
15000 |
2500 |
1-3 |
9 |
4500 |
5 |
9000 |
1125 |
2-3 |
5 |
6000 |
2 |
9000 |
1000 |
2-4 |
6 |
8500 |
3 |
14000 |
1833.33 |
3-4 |
6 |
8000 |
3 |
12000 |
1333.33 |
4-5 |
8 |
9000 |
4 |
15000 |
1500 |
|
|
43500 |
|
74000 |
|
$\text{Cost Slope} = \frac{\text{Crash Cost - Normal Cost}}{\text{Normal Time - Crash Time}}$
Stage 1 :- Normal Time:-
Critical path = 1-2-3-4-5
Project duration = 26 days
Stage 2 :- All Crash
Critical path = 1-2-6-4-5
Project Duration = 13 days
Stage 3 :- Stage 1 + Crash C by 3 days & Crash E by 1 day.
Critical path = 1-2-3-4-5 or 1-3-4-5
Project duration = 22 days
Stage 4 : - Stage 3 + Crash D by 3 days & Crash E by 2 days.
Critical path = 1-2-3-4-5
1-3-4-5
Project duration = 20 days
Stage |
Description |
Duration |
Direct |
Indirect |
Addition |
Total |
I |
All Normal |
26 |
43500 |
26×3500=91000 |
- |
134500 |
II |
All Crash |
13 |
74000 |
13×3500=45500 |
- |
19500 |
III |
Stage I+ Crash C by 3 days and Crash E by 1 day |
22 |
43500 |
22×3500 |
3×1000+ 1333.33 |
124833.33 |
IV |
Stage 3 +Crash D by 3 day & Crash E by 2 day |
20 |
43500 |
20×3500 |
3000+1333.33×1833.33+2× 1333.33 |
125999.98 |
Optimum cost = Rs. 124833.33
Optimum duration = 22 days.