Activity |
Normal Duration (days) |
Normal Cost (Rs.) |
Crash Duration (days) |
Crash Cost (Rs.) |
Cost Slope |
1-2 |
6 |
7000 |
3 |
14500 |
2500 |
1-3 |
8 |
4000 |
5 |
8500 |
1500 |
2-3 |
4 |
6000 |
1 |
9000 |
1000 |
2-4 |
5 |
8000 |
3 |
15000 |
3500 |
3-4 |
5 |
5000 |
3 |
11000 |
3000 |
4-5 |
7 |
8000 |
4 |
15000 |
2333.33 |
|
|
|
38000 |
73000 |
|
$\text{Cost Slope} = \frac{\text{Crash Cost - Normal Cost}}{\text{Normal Time - Crash Time}}$
Stage 1 : - Normal Time
Critical path = 1-2-3-4-5
Project duration = 22 days
Stage 2 :- Crash Time
Critical path = 1-3-4-5
Project duration = 12 days
Stage 3 :- Stage 1+ Crash C by 2 days and Crash E by 1 day
Critical path =1-2-3-4-5 = 1-3-4-5
Project duration = 19 days
Stage 4 :- Stage 3 +Crash A by 1 day & Crash B by 1 day
Critical path = 1-2-3-4-5 = 1-3-4-5
Project duration = 18 days
Stage |
Description |
Duration |
Direct |
Indirect |
Addition |
Total |
1 |
All Normal |
22 |
38000 |
22,5000=11000 |
- |
148000/- |
2 |
All Crash |
12 |
73000 |
12,5000=60000 |
- |
133000/- |
3 |
Stage 1+ Crash C by 2 days and Crash E by 1 day |
19 |
38000 |
19,5000=95000 |
2,1000+1,3000 |
138000/- |
4 |
Stage 3 +Crash A by 1 day & Crash B by 1 day |
18 |
38000 |
18,5000=90000 |
5000+1,2500+1,2500 |
137000/- |
∴ Optimum cost = Rs. 137000/-
Optimum duration = 18 days