For a small project, prepare resource histogram based on EST and LFT schedule and comment the suitability of distribution on above methods.
Activity | Preceding Activity | Duration (day) | Workers |
---|---|---|---|
A | - | 4 | 2 |
B | - | 5 | 3 |
C | - | 3 | 5 |
D | A | 4 | 4 |
E | B | 5 | 3 |
F | C | 3 | 5 |
G | E | 7 | 6 |