Prepare time scaled version network and histogram for EST and LST schedule.
written 6.9 years ago by | • modified 2.8 years ago |
Following table shows activities, their durations and labour requirement.
Activity | Immediate Predecessor | Duration (days) | Labours |
---|---|---|---|
A | - | 4 | 9 |
B | - | 2 | 3 |
C | - | 2 | 6 |
D | - | 4 | 4 |
E | B | 3 | 8 |
F | C | 2 | 7 |
G | D, F | 3 | 2 |
H | E, G | 4 | 1 |
Prepare time scaled version network and histogram for EST and LST schedule. Which schedule will you prefer? Why?