If only 10 labours are available, then how will you schedule the activities?
Activities 1-2 1-3 2-3 2-4 3-5 4-5
Duration 8 8 8 4 9 6
Labour / Day 4 6 5 3 6 5
1 Answer
0
0views
Activities Duration EST EFT LST LFT Labour / Day
1-2(A) 8 0 8 0 8 4
1-3(B) 8 0 8 8 16 6
2-3(C) 8 8 16 8 16 5
2-4(D) 4 8 12 15 19 3
3-5(E) 9 16 25 16 25 6
4-5(F) 6 12 18 19 25 5

enter image description here

Project duration = 25 days

Critical path =1-2-3-5

enter image description here

The activities cannot be scheduled because there are 14 labours available which is greater than 10 and the activity adjustment dose not fulfill the condition.