Job/Site layout can be defined as site space allocation for material storage, working areas, units of accommodation, plant positions, general circulation areas and also access and egress for deliveries and emergency services.
It is imperative that every construction project should be organized and executed in the most economical and safest manner.
To aid on the smooth execution of the project, a job layout is prepared.
This a scaled drawing of the proposed construction site showing all the relevant features such as entry and exit points to the site, storage areas for materials, contractors offices, area keeping for equipments such as mixer, bar bending area, labour housing, toilets etc.
It is also necessity that first aid kits are kept in the site engineer’s office.
The following factors should be considered in preparing site layout:
The following are the advantages of a good job layout: -