A small project consists of following activities. Draw network. Mark critical path. Determine project duration.

Mumbai University > Civil Engineering > SEM 8 > Construction Management

Marks: 12M

A small project consists of following activities. Draw network. Mark critical path. Determine project duration. Find out the values of all type of float:-

Activity Preceding,Activity Duration (days)
P - 3
Q - 5
R - 7
S P, Q 5
T S, R 3
U S, R 4
V S, R 6
W U, V 8
X U, V 6
Y T, W 4
1 Answer
1
25views
Activity Preceding,Activity Duration (days) EST EFT LST LFT TF FF Int F Ind F
P - 3 0 3 2 5 2 0 2 0
Q - 5 0 5 0 5 0 0 0 0
R - 7 0 7 3 10 3 3 0 3
S P, Q 5 5 10 5 10 0 0 0 0
T S, R 3 10 13 22 24 12 11 1 11
U S, R 4 10 14 12 16 2 0 2 0
V S, R 6 10 16 10 16 0 0 0 0
W U, V 8 16 24 16 24 0 0 0 0
X U, V 6 16 16 22 28 4 2 2 2
Y T, W 4 24 28 24 28 0 0 0 0

enter image description here

Critical path = 10-30-40-60-70-80

Critical activity = Q-S-V-W-Y

Project duration = 28 Days