Identify the project duration & critical path.
written 6.9 years ago by | • modified 2.8 years ago |
Mumbai University > Civil Engineering > SEM 8 > Construction Management
Marks: 12M
A network consists of the following activities:
a) Draw the networks.
b) workout the floats.
c) Identify the project duration & critical path.
Sr. No. | Activity | Preceding Activity | Following Activity | Duration (days) |
---|---|---|---|---|
1 | P | - | U | 15 |
2 | Q | - | S, T | 19 |
3 | R | - | - | 29 |
4 | S | Q | V, W | 14 |
5 | T | Q | X | 09 |
6 | U | P | X | 14 |
7 | V | S | X | 02 |
8 | W | S | - | 15 |
9 | X | U, V, T | - | 11 |