Draw an A-O-L diagram

Mumbai University > Civil Engineering > SEM 8 > Construction Management

Marks: 10M

Draw an A-O-L diagram for the following data:-

Find:-

1) Project duration

2) Critical Path

3) Activity times

4) Total float & free float values.

Activity Predecessor Duration (days)
A - 4
B A 5
C A 3
D A 5
E - 2
F - 3
G B, D 5
H C, D 4
I G, H 3
1 Answer
0
4views
Activity Predecessor Duration (days) EST EFT LST LFT T.F. F.F.
A - 4 0 4 0 4 0 0
B A 5 4 9 4 9 0 0
C A 3 4 7 7 10 3 2
D A 5 4 9 4 9 0 0
E - 2 0 2 15 17 15 15
F - 3 0 3 14 17 14 0
G B, D 5 9 14 9 14 0 0
H C, D 4 9 13 10 14 1 1
I G, H 3 14 17 14 17 0 0

enter image description here

Critical path = 10-20-40-50-70-80 or 10-20-50-70-80

Project duration = 17 days