Draw an A-O-L diagram
written 6.9 years ago by | • modified 2.8 years ago |
Mumbai University > Civil Engineering > SEM 8 > Construction Management
Marks: 10M
Draw an A-O-L diagram for the following data:-
Find:-
1) Project duration
2) Critical Path
3) Activity times
4) Total float & free float values.
Activity | Predecessor | Duration (days) |
---|---|---|
A | - | 4 |
B | A | 5 |
C | A | 3 |
D | A | 5 |
E | - | 2 |
F | - | 3 |
G | B, D | 5 |
H | C, D | 4 |
I | G, H | 3 |