Draw A-O-A diagram using network rules. Determine critical path & project duration. Determine all float values for all activities.

Mumbai University > Civil Engineering > SEM 8 > Construction Management

Marks: 10M

Draw A-O-A diagram using network rules. Determine critical path & project duration. Determine all float values for all activities.

Activity Immediate predecessor Duration (days)
A - 3
B A 5
C A 7
D A 9
E B, C 11
F D 5
G F 6
H - 8
I E 13
J G, H, I 16
1 Answer
0
107views

Int float = T.F.-F.F.

Activity Immediate Predecessor Duration (days) EST EFT LST LFT TF FF Ind F Int F
A - 3 0 3 0 3 0 0 0 0
B A 5 3 8 5 10 2 0 0 2
C A 7 3 10 3 10 0 0 …