Draw A-O-A diagram using network rules. Determine critical path & project duration. Determine all float values for all activities.
written 6.9 years ago by | • modified 2.8 years ago |
Mumbai University > Civil Engineering > SEM 8 > Construction Management
Marks: 10M
Draw A-O-A diagram using network rules. Determine critical path & project duration. Determine all float values for all activities.
Activity | Immediate predecessor | Duration (days) |
---|---|---|
A | - | 3 |
B | A | 5 |
C | A | 7 |
D | A | 9 |
E | B, C | 11 |
F | D | 5 |
G | F | 6 |
H | - | 8 |
I | E | 13 |
J | G, H, I | 16 |