written 6.9 years ago by | • modified 2.8 years ago |
Mumbai University > Civil Engineering > SEM 8 > Construction Management
Marks: 10M
written 6.9 years ago by | • modified 2.8 years ago |
Mumbai University > Civil Engineering > SEM 8 > Construction Management
Marks: 10M
written 6.9 years ago by |
In CPM, a fixed duration is used for each activity based on previous experience and knowledge. In that sense, it can be deterministic.
Also, in CPM, the critical path is determined on the basis of critical activities i.e. float calculations are performed for all activities to find out the critical activities, and the critical path. Hence CPM is an activity oriented network.
On the other hand, in PERT, three probable time estimates based on probability distribution are assigned to an activity, which then give the most likely time estimate. Hence, PERT can be said to be probabilistic network.
Also, in PERT, the critical path is determined on the basis of critical events i.e. slack calculations are done to determine path is determined on the basis of critical events i.e. slack calculations are done to determine the critical events and hence, the critical path.
Hence PERT is an event oriented network.
The different PERT time estimates are as follows:-