written 8.7 years ago by |
Software Project Management - May 2014
Information Technology (Semester 8)
TOTAL MARKS: 100
TOTAL TIME: 3 HOURS
(1) Question 1 is compulsory.
(2) Attempt any four from the remaining questions.
(3) Assume data wherever required.
(4) Figures to the right indicate full marks.
1(A) What are PMBOK knowledge areas?(5 marks)
1(B) Compare various project implementation approaches.(5 marks)
1(C) What is the need of IT project management?(5 marks)
1(D) Compare various formal organizational structure.(5 marks)
1(E) Define:
Scope grope,
Scope creep
Scope leap
Projectities
Earned values.(5 marks)
2(A) Define project.Explain the attributes of project.(10 marks)
2(B) Explain project estimation techniques.(10 marks)
3(A) Explain the phases of project life cycle.Compare it with SDLC.(10 marks)
3(B) What is outsourcing?Explain project procurement management.(10 marks)
4(A) Explain IT project risk identification framework.(10 marks)
4(B) Explain the change management plan.(10 marks)
5(A) Explain the practices of exemplary leadership.What are the leadership styles?(10 marks)
5(B) Explain scope management processes.(10 marks)
6(A) Explain project planning framework(10 marks)
6(B)
Define critical path.Draw AON diagram, find critical path and float non critical path for following:
Activity | Predecessor | Duration in days |
A | --------- | 6 |
B | A | 5 |
C | A | 8 |
D | B,C | 4 |
E | C | 3 |
F | D | 2 |
G | D | 4 |
H | E,F,G | 7 |
(10 marks)
Any Two
7(A) Write short on any
Ethical leadership and ethical dilemmas(10 marks)
7(B) Resource loading(10 marks)
7(C) Project communication management(10 marks)
7(D) Work break down structure(10 marks)