written 7.4 years ago by |
Hydrology & Water Resources Engineering - May 2015
Civil Engineering (Semester 5)
TOTAL MARKS:
TOTAL TIME: HOURS
1 (a) Differentiate between low and high head power plants. Discuss components of a hydroelectric power plant(7 marks)
1 (b) With a neat sketch, describe various zones of storage in a reservoir. Also suggest measures to control reservoir sedimentation(7 marks)
2 (a) What is the need for planning of water resources projects? Discuss the steps involved in the water resources planning.(7 marks)
2 (b) Discuss causes of drought and drought contingency planning.(7 marks)
2 (c) What is meant by 'water harvesting'? Explain methods of roof water harvesting and water harvesting for agricultural use.(7 marks)
3 (a) i) Explain various forms of precipitation.(3 marks)
3 (a) ii) Explain the use of tipping bucket type rain gauge.(4 marks)
3 (b) The rates of rainfall for successive 30 minute period of a 3-hour storm are 1.5, 3.2, 4.3, 2.7, 2.1 and 1.2 cm/hr. The surface runoff in response to the
storm is estimated to be 3.0 cm. Determine ϕ-index and w-index. Consider a
total of depression and interception losses of 1.0 cm.(7 marks)
3 (c) i) A rain gauge 'D' was inoperative during a specific storm. The rainfall
recorded at three surrounding stations A, B and C during that storm were
52, 85 and 70 mm respectively. If the average annual rainfall of stations
A, B, C and D are 650, 900, 820 and 700 mm respectively, estimate the
storm rainfall of station D.(3 marks)
3 (c) ii) The rainfall values at gauging stations and corresponding areas of
Thiessen's polygons for a drainage basin are as follows:
Station | A | B | C | D | E | F | G |
Area of Thiessen's Polygon (km2) | 160 | 135 | 92 | 110 | 68 | 70 | 35 |
Rainfall (cm) | 10.0 | 13.5 | 9.1 | 12.6 | 11.2 | 14.0 | 10.8 |
Compute the average rainfall over the basin.(4 marks) 3 (d) What are the factors that affect Evaporation? Describe any one method of measurement of evaporation.(7 marks) 4 (a) Explain procedure to derive s-curve hydrograph from a given unit hydrograph. What are the uses of s-curve hydrograph?(7 marks) 4 (b) Discuss occurrence of groundwater with a neat sketch and define various water bearing formations.(7 marks) 4 (c) Define Hydrograph. Draw a typical single-peaked hydrograph and explain its components.(7 marks) 4 (d) The ordinates of flood hydrograph for a drainage basin in response to a 6- hour storm are observed as follows:
<colgroup span="9" style="text-align: center;" width="85"> </colgroup>
Time (hour) | 0 | 3 | 6 | 9 | 12 | 15 | 18 | 21 |
Hydrograph Ordinate (cumec) | 15 | 35 | 67 | 109 | 151 | 175 | 195 | 153 |
<colgroup span="9" style="text-align: center;" width="85"> </colgroup>
Time (hour) | 24 | 27 | 30 | 33 | 36 | 39 | 42 | 45 |
Hydrograph Ordinate (cumec) | 139 | 113 | 87 | 63 | 47 | 31 | 23 | 15 |
Considering total rainfall of 7 cm during the storm, average rate of infiltration loss of 0.5 cm/hr and a constant base flow of 15 cumec, derive ordinates of the 6-hour unit hydrograph. Also estimate area of the basin.(7 marks) 5 (a) Discuss causes of flood.(7 marks) 5 (b) Explain flood routing through reservoirs.(7 marks) 5 (c) Write a short note on flood control by constructing levees and flood walls.(7 marks) 5 (d) Briefly explain method of estimating design flood for a water resources Project.(7 marks)