written 7.4 years ago by |
Hydrology & Water Resources Engineering - May 2016
Civil Engineering (Semester 5)
TOTAL MARKS:
TOTAL TIME: HOURS
1 (a) Describe non-automatic and automatic rain gauges. Explain the merits and
demerits of each.(7 marks)
1 (b) A thunder storm of 6hour duration produces the following flood hydrograph.
Derive the ordinates of unit hydrograph for a catchment area of 2845 km2. Also
sketch the resulting unit hydrograph.
Date | July 3 | July 4 | July 5 | |||||||
Time (hour) | 6 am | 12 noon | 6 pm | 12 mid night | 6 am | 12 noon | 6 pm | 12 mid night | 6 am | 12 noon |
Discharge (m3/sec) | 100 | 400 | 1500 | 3500 | 5100 | 3000 | 1500 | 900 | 400 | 100 |
If the volume of measured runoff due to storm is 1.4×106 m3, estimate the φ-index of the basin.
Time from start of storm (hours) | 0 | 2 | 4 | 6 | 8 | 10 | 12 | 14 |
Accumulated rainfall (mm) | 0 | 8 | 18 | 59 | 68 | 83 | 89 | 95 |
Solve any one question from Q2(b) & Q2(c)
2 (b) Define the following with figure
(1) Earthen dam
(2) Gravity dam
(3) Arch dam
(4) Buttress dam
(5) Spillway(7 marks)
2 (c) Describe in detail the factors affecting infiltration.(7 marks)
Solve any two question from Q3(a), Q3(b) & Q3(c), Q3(d)
3 (a) Define unit hydrograph and its uses. Clearly explain the assumption made in the derivation of unit hydrograph.(7 marks)
3 (b) Define the following
(1) Aquifer
(2) Aquiclude
(3) Aquifuge
(4) Specific yield
(5)
Specific retention
(6) Storage coefficient
(7) Transmissibility coefficient(7 marks)
3 (c) Explain Darcy's law with its limitations. Describe the procedure of proving it
Experimentally.(7 marks)
3 (d) Describe in brief
(1) Reservoir sedimentation
(2) Reservoir capacity(7 marks)
Solve any two question from Q4(a), Q4(b) & Q4(c), Q4(d)
4 (a) Describe the various components of a typical hydropower plant with a neat sketch.
Also discuss the function of each component.(7 marks)
4 (b) Describe the situations under which the following dams are constructed
(1)
Gravity dam
(2) earthen dam
(3) Arch dam.
Also describe any two major
reservoirs of India.(7 marks)
4 (c) Define flood and its causes. Also discuss various measures taken to control the
Flood.(7 marks)
4 (d) (i) Define the following
(a) Return period
(b) Spillway design flood
(c) Probable
maximum flood(3 marks)
4 (d) (ii) bridge has an expected life of 25 years and designed for flood management of return period 100 years.
(a) What is the risk of this hydrologic design
(b) if a
10% risk is acceptable, what return period will have to be adopted.(4 marks)
Solve any two question from Q5(a), Q5(b) & Q5(c), Q5(d)
5 (a) Distinguish between
(1) Hydraulic and hydrologic method of flood routing
(2) Hydrologic storage routing and hydrologic channel routing
(3) Prism storage and wedge storage(7 marks)
5 (b) Describe the types of drought and its causes.(7 marks)
5 (c) Describe various measures of water conservation and augmentation.(7 marks)
5 (d) Describe in brief
(1) Channel improvement
(2) Flood damage analysis(7 marks)