written 8.7 years ago by |
Software Project Management - May 2013
Information Technology (Semester 7)
TOTAL MARKS: 80
TOTAL TIME: 3 HOURS
(1) Question 1 is compulsory.
(2) Attempt any three from the remaining questions.
(3) Assume data if required.
(4) Figures to the right indicate full marks.
1 (a) Compare Gantt chart, networking diagram and PDM(5 marks)
1 (b) Compare various project implementation approaches.(5 marks)
1 (c) What is the need of IT project management.(5 marks)
1 (d) Describe in brief various PMBOK knowledge areas.(5 marks)
1 (e) What is a project charter?(5 marks)
2 (a) Explain project integration management.(10 marks)
2 (b) Explain Project planning framework.(10 marks)
3 (a) Define following terms:
(i) Project.
(ii) Scope of the project.
(iii) Earned value.
(iv) Critical path.
(v) Projectitis.(10 marks)
3 (b) Explain change management plan.(10 marks)
4 (a) Explain the framework for managing IT project risk.(10 marks)
4 (b) Explain the practices of exemplary leadership.(10 marks)
5 (a) Draw AON diagram and find the activities on critical path. Calculate minimum overall project completion time:
Activity | Duration (wks) | Immediate Predecessor |
A | 2 | - |
B | 3 | - |
C | 4 | A |
D | 3 | A,B |
E | 8 | C,D |
F | 3 | C |
G | 2 | E |
H | 3 | F,G |
Write short notes on (any three):-
7 (a) Ethics in project.(7 marks) 7 (b) Project procurement and outsourcing.(7 marks) 7 (c) Extreme project management.(7 marks) 7 (d) Scope management plan.(7 marks)